PROD 1024 Advanced Principles in Lean Manufacturing
Coursework
Individually read the Farm Equipment International data set and:
1. Produce a door-to-door value stream map of the current manufacturing
process.
[25 marks]
2. Outline and answer the eight key questions for the future state design. [40 marks]
3. Thereby produce a future state map detailing the processes necessary to operate the factory according to lean manufacturing principles.
[25 marks]
4. Produce an implementation plan for the company to move from present state to future state.
[10 marks]
Notes:
Remember – this is an individual piece of coursework. If you collaborate, you risk losing all your marks!
This coursework is intended to measure the following learning outcomes:
reflect on the significance of lean theory and the application of key lean thinking principles;
critically analyse lean thinking in different engineering sectors;
formulate innovative proposals based on detailed knowledge of the tools and techniques relating to the implementation of lean thinking;
Farm Equipment International
Farm Equipment International (FEI) produces components and sub-assemblies for agriculture. Here, we are considering one product family, hydraulic control sections. These are produced in several configurations for different tractors and markets. The market for hydraulic control sections covers both original-equipment tractor assemblers and the aftermarket repair and overhaul businesses that support the agricultural industry worldwide.
As the company offers a wide variety of possible configurations, and the fact that the exact configuration each customer requires can vary from order to order, hydraulic control sections are made to order. A hydraulic control lever currently takes 27 days to go through the factory. This production lead time and a large order backlog have resulted in FEI to quote a 60 day lead time to customers. Unfortunately, FEI’s original-equipment customers can not predict their exact requirements more than 2 weeks before use. As a result they make frequent changes to the detail of their orders 2 weeks before delivery. These changes lead to frequent expediting of batches at the FEI factory.
Production Control at FEI releases customer orders to the factory approximately in the sequence that they are received, the shop floor supervisors and operators “batch” the orders together by configuration in an attempt to reduce the number of changeovers. This also leads to expediting of orders.
The product
 A hydraulic control section is a metal tube with a cast connector welded to each end.
 Hydraulic control sections are available in 30 different lengths, 3 diameters, and with 2 different types of connectors. Each end of a hydraulic control section can have a different connector. This means that FEI can potentially supply 360 different finished hydraulic control sections. It is not known what the demand for each individual specification is.
Customer requirements
 24000 hydraulic control sections per month.
 Order size varies from 20 pieces up to 200 pieces. Average order size is 50
pieces.
 5 hydraulic control sections per box.
 Several shipments each day by truck to different customers.
 Each order from each customer varies in quantity and configuration.
 FEI requires orders to arrive 60 days before shipping of finished hydraulic
control sections.
 Customers may change the mix of configurations up to 2 weeks before the
shipping date.
Production Processes
All the hydraulic control sections follow the same basic factory routing:
Cut tube Weld Weld Remove Paint Assembly 1st end 2nd end flash (contractor)
Machine Castings
 FEI’s routing for producing hydraulic control sections is to cut a metal tube to length, weld the connectors in place, deflash (remove the excess weld material), painting (done at an external contractor’s premises), and finally assembly of the connectors. The cast connectors are also machined at FEI’s factory. Finished hydraulic control sections are shipped to customers daily.
 Switching between tube lengths requires a 15 minute changeover at the cutting, welding and deflash workstations.
 Switching between tube diameters takes a 60 minute changeover at the cutting, welding and deflash operations. This longer changeover is mostly due to a “1st off” quality control inspection after such a changeover.
 Switching between each of the three types of cast connectors takes a 2 hour changeover at the machining operation.
 Tubes are supplied by Kentish Tube Systems Ltd. The lead time for obtaining tubes is 4 months (16 weeks). Kentish Tube Systems Ltd. deliver products every 2 weeks.
 Raw castings for the end connectors are supplied by Essex Castings Ltd. The lead time for obtaining castings is 3 months (12 weeks). Essex Castings Ltd. deliver products every 2 weeks.
Work Time
 20 days in a month.
 2 shifts per day in each department.
 8 hours per shift, overtime added if necessary.
 Two breaks each shift, 15 minutes per break.
o Manual processes stop for breaks o Lunch is not paid.
FEI Production Control
 Receives customer orders 60 days from shipment, and enter them to MRP system.
 Generates a “shop order” per customer order. This follows the product through the entire production process.
 Release shop orders to the factory 6 weeks before the shipment date to accelerate MRP’s ordering of tubes and castings.
 Issue a daily production list to supervisors in production departments. Supervisors schedule shop orders through their department.
 Receives customer configuration changes 2 weeks before shipment and advises department supervisors to expedite orders as necessary.
 Issues daily shipping schedule to Despatch Department.
Process Information
1. Cutting (the saw cuts tubes and rods for many FEI product families).  Manual process, 1 operator
 Cycle time = 15 seconds
 Changeover time = 15 minutes (length), 60 minutes (diameter)  Reliability = 100%
 Inventory
i. 20 days of uncut tubes
ii. 5 days of cut tubes.
2. Welding workstation 1 (dedicated to the hydraulic control sections product family)
 Welds the first machined casting to the tube
 Automatic process, with operator load and unload external to the
machine cycle
 Cycle time:
i. Operator = 10 seconds
ii. Machine = 30 seconds
 Changeover time = 15 minutes (length), 60 minutes (diameter)
 Reliability = 90%
 Inventory = 3 days of welded sections.
3. Welding workstation 2 (dedicated to the hydraulic control sections product family)
 welds the second machined casting to the tube
 Automatic process, with operator load and unload external to the
machine cycle
 Cycle time:
i. Operator = 10 seconds
ii. Machine = 30 seconds
 Changeover time = 15 minutes (length), 60 minutes (diameter)
 Reliability = 80%
 Inventory = 3 days of welded sections.
4. Deflash workstation (dedicated to the hydraulic control sections product family)
 Automatic process, with operator load and unload external to the machine cycle
 Cycle time:
i. Operator = 10 seconds
ii. Machine = 30 seconds
 Changeover time = 15 minutes (length), 60 minutes (diameter)
 Reliability = 100%
 Inventory = 5 days of deflashed sections.
5. Painting (hydraulic control sections are shipped to an outside contractor for painting)
 Painting lead time = 2 days
 One daily truck pickup of unpainted sections and drop-off of painted
sections
 Observed inventory:
i. 2 days at the painter
ii. 6 days of painted sections at FEI.
6. Connector assembly (dedicated to the hydraulic control sections product family)
 Manual process with 6 operators
 Total Work Time per Piece = 195 seconds
 Changeover time = 10 minutes fixture swap
 Reliability = 100%
 Observed finished goods inventory in warehouse = 4 days of finished
hydraulic control sections.
7. Machining of Castings (dedicated to the hydraulic control sections product family)
 Automatic machining process with one machine attendant  Cycle time = 30 seconds
 Changeover time = 2 hours
 Reliability = 100%
 Observed inventory:
i. 20 days of raw castings from the supplier
ii. 4 days of machined castings.
8. Despatch department
 Removes parts from finished goods warehouse and stages them for truck shipment to customers.

For This or a Similar Paper Click To Order Now

our services

We Are A Full Academic Writing Service 

We are a brilliant custom writing service. We specialize in supplying professional writing help for students the world over. As a professional custom writing service, we are eager to offer reliable writing assistance with all types of written assignments to students who seek our help. Thus, students who order papers with us will receive a well-formatted, informative and carefully-research custom paper.

 

We Handle Every Single Paper Type That You May Require

 

We work tirelessly to satisfy every client’s need, and this is reflected in every facet of our professional writing services. Therefore, as a student you don’t have to worry anymore about beating coursework assignment deadlines, juggling between doing a part time job and writing essays, and conducting extensive research in order to get a good grade in your paper. Just place an order with us and have your academic paper written by a professional writer with years of academic essay writing experience.

 

Writing Services

All types of academic texts will be accomplished in a heartbeat by our talented & experienced authors.

 

Editing Services

Our company’s editors are proficient in eliminating errors dealing with grammar, punctuation, terminology, etc.

 

Proofreading

Skillful proofreaders diligently scan your paper to assure apt transitions, smooth flow, and logically structured paragraphs!

 

FormTTING sERVICES

The paper’s structure, its word count, and all of the other formatting requirements will be adhered to.

 

Z

Plagiarism-free papers

Z

Complete Confidentiality

Z

100% Money-back

Z

Timely Delivery

Z

24/7 Support

Z

Experienced Writers

How We Work?

Get A Professional Writer do your Homework

Working with professional essay writers writing service couldn’t be easier. We provide you with a quick and easy to use the system, thanks to which you can be sure of the best you are looking for. Just follow the process we described in detail here, and you will soon be working with the best authors:

 

“I used the service and got A+ I like the service, the quality of work was good and my mark as well. Not expensive. And the timing was a big plus for me because I got work right when we agreed.”

Research Paper

Student

Happy Clients

Bringing security and peace of mind is our mission.

“Excellent service as always! Always above and beyond A-Level work! Highly recommend. Great work done well within the stated timelines. Great annotated bib. and great research on the paper. I went out on the limb to use this service for the first time ever, but I am absolutely overwhelmed with work work work that this took so much pressure off of me. I will definitely use you again in the future. Thank You.”

Assignment

Student

” This is an amazing resource for the students. I love the simple submission and the quality of writers.”

Essay

Student

Order an Assignment paper written from scratch on practically any subject

Serving Your Student Needs

Contact

EMAIL US

support@eliteacademicessays.com

v

Whatsapp

+1 (267) 743-9381